Marrakech, 11 July 2025

Proposal for financing collective water infrastructure Background The earthquake that struck the High Atlas Mountains in September 2023 severely affected the province of Al Haouz, causing significant material damage and heavy loss of life. This disaster highlighted the fragility of local infrastructure and raised major concerns about disaster preparedness and emergency response capacity. In this context, reconstruction efforts are essential to enable affected communities to recover and rebuild their daily lives. It is with this in mind that the AVERDHA project (Support for Economic Development and Sustainable Reconstruction of Disaster-Stricken Municipalities in the High Atlas) has been launched by VNG International, in partnership with the AMPCC (Moroccan Association of Municipal Council Presidents). This project supports four particularly affected municipalities (Asni, Talat N'Yaacoub, Ighil and Aghbar) in rebuilding community facilities and revitalising the economy and society in their areas. Through technical and financial support, AVERDHA aims to meet the urgent needs identified by the municipalities, particularly in terms of access to drinking water. The water infrastructure, which was severely damaged by the earthquake, requires rapid intervention. Among the issues identified are: •

Cracked or completely destroyed reservoirs;

•

Relocation of villages to new, more stable sites, but lacking all basic public facilities, including water supply systems.

Faced with this situation, the AVERDHA project, in close coordination with local councils and government departments, has committed to financing the construction and/or reconstruction of certain water facilities. However, the needs expressed by the population far exceed the project's financial capacity.

1

Aware of this limitation, VNG International is currently seeking to mobilise additional funding. In order to better assess the investments required to carry out these works, a technical study has been commissioned to conduct: A detailed technical study for the construction of drinking water reservoirs and other community infrastructure in the affected villages.

•

Proposed equipment Drinking water storage tanks play an essential role in the stability of communities and are a crucial link in the water supply system. Aware of their importance, the AVERDHA project proposes to finance the construction of five (5) drinking water reservoirs for the two partner municipalities most severely affected by the earthquake. These two municipalities alone comprise more than 40 villages (douars). Municipality Ighil

Aghbar

Village

Community facilities

Amskrajen Lbour

Construction of a 40 m3 semi-underground reservoir Construction of a 40 m3 semi-underground reservoir

Tazgzaout Lmkayate

Construction of a 40 m3 semi-buried reservoir Construction of a 50 m3 semi-underground tank

Agadir Ijanatne

Construction of a 40 m3 semi-buried tank

Results of the assessment of the proposed equipment 1. Amskrajn village The douar of Amskrajn, which has 40 families, or about 160 inhabitants, is one of the localities that became uninhabitable following the 2023 earthquake. The population is gradually moving to a new site, where 16 houses are being rebuilt. The other households will join them , , fur , and , as appropriate. as needed. This relocation has required the establishment of new basic social infrastructure, in particular access to drinking water. In this context, the local population has expressed the need to build a

2

drinking water storage tank on an elevated point on the new site to ensure efficient distribution. The residents have committed to preparing the ground for the reservoir, demonstrating their active involvement in the success of this project. Reservoir to be designed

3

◼ Estimated cost breakdown for the work No

Designation of works

Unit

Qty

Unit

Total price

I

TANK

1

Excavation in trenches in solid ground or wells in any type of terrain, even in rock

M

77.7

8

6,220

2

Backfilling or disposal at public landfills

M3

37

5

1,860

3

Clean concrete

M3

2.70

90

2,430

4

Dry stone wall

M

27

4

1,

5

Water-repellent concrete

M3

20

2,300

46,000

6

Rubble masonry

M2

47

700.00

33,488.00

7

HA steel

kg

1973.00

16

31,568.00

8

Water-repellent coating

M2

76

2

15,200

9

Reinforced concrete parapet including smooth render

ML

21

3

6,30

10

Sloping shape for terraces.

M2

27

70

1,890

11

Tile covering

M

74

25

18,500

12

Vinyl paint on exterior walls

M

66.5

2

1,331

1

Manhole cover 0.80 x 0.80

U

1

80

800

14

Galvanised steel ventilation tube

U

1

30

30

15

Sheet metal hatch

U

2

50

1,00

1

Galvanised metal ladder

Ml

3

20

60

17

Galvanised steel pipe Ø 63

M

12

20

2,400.00

18

2" gate valve

U

2

80

1,600 172,568

SUB-TOTAL RESERVOIR TOTAL EXCLUDING TAX

172,568

TOTAL VAT (20%)

34,513.60

TOTAL INCLUDING TAX

207,081.60

4

2. Lbour Village The village of Lbour is a new reception site for the disaster-stricken population of the douar of Oddift, classified as uninhabitable following the 2023 earthquake. This displacement led the inhabitants of Oddift to settle in Lbour, where there is a communal hostel and a secondary school. Currently, displaced families are living in tents, supplied with drinking water via a communal reservoir originally intended for existing public buildings. The site is designed to accommodate all 57 affected families, or approximately 288 inhabitants. Several houses are already under construction, making it essential to install a new drinking water storage tank to meet growing needs. The residents have committed to preparing the land for the construction of the tank, demonstrating their commitment to improving their living conditions in the long term. Reservoir to be designed

5

◼ Estimated price list for the work No

Designation of works

Unit

Qty

Unit

Total price

I

TANK

1

Excavation in trenches in solid ground or wells in any type of terrain, even in rock

M

77.7

8

6,220

2

Backfilling or disposal at public landfills

M3

37

5

1,860

3

Clean concrete

M3

2.70

90

2,430

4

Dry stone wall

M

27

4

1,

5

Water-repellent concrete

M3

20

2,300

46,000

6

Rubble masonry

M2

47

70

33,488

7

HA steel

kg

1973

20

39,460.00

8

Water-repellent coating

M2

76

2

15,200

9

Reinforced concrete parapet including smooth render

ML

21.00

300.00

6,300.00

10

Sloping shape on terrace.

M2

27

70

1,890

11

Tile covering

M

74

25

18,500

12

Vinyl paint on exterior walls

M

66.5

2

1,331

1

Manhole cover 0.80 x 0.80

U

1

80

800

14

Galvanised steel ventilation tube

U

1

30

30

15

Sheet metal hatch

U

2

50

1,00

1

Galvanised metal ladder

Ml

3

20

60

17

Galvanised steel pipe Ø 63

M

12

20

2,400

18

2" gate valve

U

2

80

1,600 180,460

SUB-TOTAL RESERVOIR TOTAL EXCLUDING TAX

180,460

TOTAL VAT (20%)

36,092

TOTAL INCL. VAT

216,552.00

6

3. Tazgzaout village The village of Tazgzaout has around sixty families, or nearly 240 inhabitants. Following the 2023 earthquake, the village is gradually being relocated to the other side of the wadi. Currently, 20 houses are under construction on the new site, while the other families follow. The douar benefits from a water source located in the wadi, equipped with a pumping system powered by solar panels. The only thing missing to ensure the supply of drinking water is the construction of a reservoir on a raised point on the new site. The local population has committed to uprooting the almond trees on the identified site and preparing the ground for the construction of the reservoir. Reservoir to be designed

7

◼ Estimated price list for the work No

Designation of works

Unit

Qty

Unit

Total price

I

TANK

1

Excavation in trenches in solid ground or wells in any type of terrain, even in rock

M

77.7

8

6,220

2

Backfilling or disposal at public landfills

M3

37

5

1,860

3

Clean concrete

M3

2.70

90

2,430

4

Dry stone wall

M

27

4

1,

5

Water-repellent concrete

M3

20

2,300

46,000

6

Rubble masonry

M2

47

70

33,488

7

HA steel

kg

1973.00

16

31,568.00

8

Water-repellent coating

M2

76

2

15,200

9

Reinforced concrete parapet including smooth render

ML

21

3

6,30

10

Sloping shape for terraces.

M2

27

70

1,890

11

Tile covering

M

74

25

18,500

12

Vinyl paint on exterior walls

M

66.5

2

1,331

1

Manhole cover 0.80 x 0.80

U

1

80

800

14

Galvanised steel ventilation tube

U

1

30

300.00

15

Sheet metal hatch

U

2

50

1,00

1

Galvanised metal ladder

Ml

3

20

60

17

Galvanised steel pipe Ø 63

M

12

20

2,400

18

2" gate valve

U

2

80

1,600 172,568

SUB-TOTAL RESERVOIR TOTAL EXCLUDING TAX

172,568

TOTAL VAT (20%)

34,513.60

TOTAL INCLUDING TAX

207,081.60

8

4. Lmkayate Village The village of Lmkayate, severely affected by the earthquake, has about a hundred families, nea 400 inhabitants. Classified as a high-risk seismic zone and identified as an uninhabitable red zone, the village has been relocated to the other side of the wadi.

or

This relocation requires the construction of a new reservoir xml-ph-0001@deepl.internal reservoir on high ground on the new site reserved for the reconstruction of dwellings. It also involves the installation of water supply pipes from the well located in the wadi, as well as the installation of a drain and a water return channel to the douar. Spray tank

9

◼ Estimated price list for the work No

Designation of works

Unit

Qty

Unit

Total price

I

TANK

1

Excavation in trenches in solid ground or wells in any type of terrain, even in rock

M3

84

8

6,720

2

Backfilling or disposal at public landfills

M3

39

5

1,950

3

Clean concrete

M3

3.2

90

2,880

4

Dry stone wall

M

3

4

1,210

5

Water-repellent concrete

M3

21.95

2,000

43,900

6

Rubble masonry

M2

57.12

70

39,984

7

HA steel

kg

16

35,184

8

Water-repellent coating

M2

85

2

17,000

9

Concrete acroterion including smooth render

ML

22

30

6,60

10

Sloping shape on terrace.

M2

27

70

1,890

11

Tile covering

M

85

25

21,250

12

Vinyl paint on exterior walls

M

70

20

1,400

1

0.80 x 0.80 manhole cover

U

1

80

800

14

Galvanised steel ventilation tube

U

1

30

30

15

Sheet metal hatch

U

2

50

1,00

1

Galvanised metal ladder

Ml

3

200

60

17

Galvanised steel pipe Ø 63

M

12

20

2,400

18

2" gate valve

U

2

80

1,600

2,199

SUB-TOTAL TANK

186,668.00

II

PIPES

1

Excavated material, rocky ground

M

4

1

5,760

2

Excavated fill

M3

4

8

3,200

3

Installation bed

M3

20

300

6,000

4

Pipe DN63 PN16

ML

200

50

10,000

7

Suction cup manhole cover

U

1

12,000.00

12,000

SUB-TOTAL PIPE

36,960 TOTAL EXCLUDING TAX

223,628

TOTAL VAT (20%)

44,725.60

TOTAL INCLUDING TAX

268,353.60

10

5. Agadir Village Located at the edge of the municipality of Aghbar, on the border with the province of Taroudant, the village of Agadir has 85 families, or approximately 340 inhabitants. The population lives mainly from subsistence farming and extensive sheep and goat farming. Following the 2023 earthquake, the former site of the douar was classified as a seismic risk zone, forcing residents to rebuild their homes on a new, safer site. This displacemen involves mise place of basic infrastructure, in particular access to drinking water. A project to build a drinking water storage tank is planned on high ground at the new site to ensure efficient distribution. The local population has committed to cleaning and preparing the site for the tank. Reservoir

11

◼ Estimated price list for the work No

Designation of works

Unit

Qty

Unit

Total price

I

TANK

1

Excavation in trenches in solid ground or wells in any type of terrain, even in rock

M

77

1

9,331

2

Backfilling or disposal at public landfills

M3

37

50

1,860

3

Clean concrete

M3

2.70

90

2,430

4

Dry stone wall

M

27

4

1,

5

Water-repellent concrete

M3

20

2,000

40,000

6

Rubble masonry

M2

47.84

70

33,488

7

HA steel

kg

1973.00

16

31,568

8

Water-repellent coating

M2

76

2

15,200

9

Reinforced concrete parapet including smooth render

ML

21

3

6,30

10

Sloping shape for terraces.

M2

27

70

1,890

11

Tile covering

M

74

25

18,500

12

Vinyl paint on exterior walls

M

66.5

2

1,331

1

Manhole cover 0.80 x 0.80

U

1

80

800

14

Galvanised steel ventilation tube

U

1

30

30

15

Sheet metal hatch

U

2

50

1,00

1

Galvanised metal ladder

Ml

3

20

60

17

Galvanised steel pipe Ø 63

M

12

20

2,400

18

2" gate valve

U

2

80

1,600 169,678.40

SUB-TOTAL RESERVOIR

II

PIPES

1

Excavated material

M3

4

8

3,840

2

Excavation fill

M3

4

50

2,00

3

Installation bed

M3

20

30

6,000

5

Pipe DN63 PN16

ML

20

5

10,00

SUB-TOTAL PIPE

21,840 TOTAL EXCLUDING TAX

191,518.40

TOTAL VAT (20%)

38,303.68

TOTAL INCLUDING TAX

229,822.08

12

Summary table of the budget required for the municipalities of Aghbar and Ighil Municipalit y Ighil

Aghbar

Community facilities

Cost in MAD Including

Amskrajen

Construction of a 40 m3 semi-underground reservoir

207,081.60

Lbour

Construction of a 40 m3 semi-underground reservoir

216,552 £207,081

Village

Tazgzaout

Construction of a 40 m3 semi-underground tank

Lmkayate

Construction of a 50 m3 semi-underground reservoir

Agadir Ijanatne

Construction of a 40 m3 semi-underground reservoir Total in MAD including VAT

268,353.60 229,822.08 1,128,890

The budget required for the construction of these community facilities is approximately 1,128,890.00 Moroccan dirhams including VAT. This is equivalent to approximately 107,514.00 euros including VAT.