BESTSELLER Presentation Lelystad 15.03.22
Tekst van het document
Lelystad, NL 1
March 15th, 2022
Topics Who is BESTSELLER
Fashion Forward
Site Vision
Approach to Buildings
Timeline
Strategic Considerations 2
Head office in Brande – Where it all started
Distribution Flagship, DK
Link to design video
Office Building, Aarhus DK
3
BESTSELLER Retail Concept Store
Fashion Forward CO2 Neutral Fuel
4
Biodiversity
Solar Park
Circularity
Site Vision Operational: 24/7 - ~350 days/year
The Building
Built for Speed in execution Architectural and esthetic look & feel People in focus
The Location
The terminal
C l o s e t o BE S T S E L L E R
Lelystad
Ports
Sustainable Daily Levels
Ingoing
Warehouse
Outgoing
150 Containers
2 mill. Cartons
240 Trucks
~136.000 orders
100.000 Cartons
The People
The Size 5
Customers
A place where people are proud of working
125.000 Cartons
C l o s e t o BE S T S E L L E R
A place where people are motivated & engaged
A place that takes care of its people - Just like family
~500 People A place that develops and grows its people
Labour Vision
Key Positions
Hiring
Attracting and aquiring talent - Collaboration with college - Collaboration with local recruitment office - Local firms
Workforce Projections
6
- BESTSELLER education program options
WHS Employee
Short term WHS Employee
Mgmt. & Enabling
Techinal Specialist
Total Expected Workforce
2026
160
70
70
20
320
2028
271
90
118
34
513
- IBT
- Apprentice program - Student worker
Approach to Buildings
7
DESIGN
FEELINGS
SUSTAINABILITY
PART OF SURROUNDINGS
NATURE
PEOPLE FOCUSED
Preliminary Building Design Ideas
8
Timeline
Level Plan
2023
-
Acquisi tio n of l and
-
Municipalit y Pl anni ng
-
MHE suppl i er sel ecti o n
-
Building concept & desi g n
-
Archite c t sel ecti o n
-
People
Collaboration
Lelystad Municipality
BESTSELLER High
2022
9
-
Fi naliz ed design of bui ldin g and MHE
-
Contracto r selectio n
-
Groundb r ea kin g
-
Geol ogi cal surveys
-
Land preparati o n -
Appl i cati on for Zoning Plan
-
Appl i cati on for Building Permit -
Termi nal setup
-
Peopl e onboardin g
-
Infrastruc tu r e readin es s
2024
2025
2026
Construc tio n
-
MHE installation
-
Go live
-
Organiz ation & structu r e
-
Operational setup
-
Ramp up
-
Start people onboardin g
-
Flow setup
-
Burn In
-
Test & commissioni n g
-
Training
-
Strategic Considerations The Terminal
Scaling
The Organization
The Infrastructure
Availability Roads & Access
Flow
Capabilities Consumption e.g. Electricity ,
Readiness
10
Ramp Up
sewage, Nitrogin
11