How regret cost shapes the irreversibility of renewable energy megaprojects?
The case of the Ashalim thermal solar power station AVRI EITAN ITAY FISCHHENDLER
ALFONS VAN MARREWIJK
Avri Eitan
What will we talk about today? Background Motivation Case study and methodology Results Conclusions What’s next?
2
Avri Eitan
The global diffusion of RE
Background
Motivation
Case study
Results
Conclusions
What’s next?
3
Avri Eitan
Decentralized RE VS megaprojects
VS Background
Motivation
Case study
Results
Conclusions
What’s next?
4
Avri Eitan
What are megaprojects?
“A megaproject is not only big, in terms of scope andprojects scale and costs,endeavors, it isthe also big requiring in its “Non-routine temporary In Israel: managed by Accountant Billion$funding, projects? special authorization, potential for1+ politics in and revenues, around theand General? regulatory et al., 2011). project”actions” (Pitsis et(Scott al., 2018:6).
Background
Motivation
Case study
Results
Conclusions
What’s next?
5
RE megaprojects: characteristics Provide significant amounts of clean and sustainable energy.
Large size and centralized locations. Centralized management (private and public actors). Long time span from initiation to delivery. Enormous budget, structural complexity and high uncertainty. Significant environmental impact (positive and negative). A symbol of economic power, energy independence, and technological progress.
Background
Motivation
Case study
Results
Conclusions
What’s next?
6
Avri Eitan
RE megaprojects: problems RE megaprojects often continue to be developed with limited changes, despite the emergence of superior technologies along the way. Influenced by various lock-ins, the regret cost escalates regulators' commitment to megaprojects, leading to their suboptimal outcomes, and eventually to their irreversibility.
Background
Motivation
Case study
Results
Conclusions
What’s next?
7
Avri Eitan
Lock-ins, regret cost and escalation of commitment
Path dependent lock-ins
• “How one path becomes dominant due to selfreinforcing processes and absorbing states, and this causes the economy to lock itself in to an outcome which is not necessarily superior to alternative ones, not easily altered and not predictable in advance" (Arthur, 1989:128).
Regret cost
• The price that needs to be paid in order to regret previous decisions and change megaprojects' course of action (Leib & Buckle, 2012).
Escalation of commitment
• “The tendency to ‘carry on’ with questionable endeavors, regardless of whether doing so is likely to result in success” (Sleesman et al., 2018:178).
Background
Motivation
Case study
Results
Conclusions
What’s next?
8
Avri Eitan
The fate of RE megaprojects: The balance between regret costs and regret benefits Exit doors
Lock-ins
Regret Benefits
Regret Costs
Background
Motivation
Case study
Results
Conclusions
What next?
10
Avri Eitan
RE megaprojects: research question Research gap
Research question
• The literature has neglected the role of lock-ins in the framework of RE, which so far has been regarded as malleable.
• How do lock-ins shape the irreversibility of RE megaprojects, through the framework of regret cost?
• Exploring the irreversibility of RE megaprojects is highly important due to the significant growth of decentralized RE alternatives, which questions the necessity of such RE megaprojects. Significance
Background
Motivation
Case study
Results
Conclusions
What’s next?
11
Avri Eitan
Case study The planning and construction process (2007-2018) of the giant thermal solar power station built near a small community settlement in southern Israel, Ashalim – Focusing on plot A (150 MW). Using a qualitative case study approach (Yin, 2003) in order to provide a understanding of the constructed social reality during the planning and construction of infrastructures (Yanow & Schwartz-Shea, 2015).
Background
Motivation
Case study
Results
Conclusions
What’s next?
12
Avri Eitan
Sources of information No
Source
Data type
Public information
1
Prime Minister's Office
Official government decisions
Yes
2
Ministry of Finance
Internal meetings protocols; official governmental
No
agreements (BOT, financial closure); official tender's documents 3
4
Ministry of Energy and the
Ministerial decisions and regulations; data about
Electricity Authority
the Israeli electricity sector
Third party organizations
Position papers about the thermal solar power
Yes
Partial
station in Ashalim, and the Israeli electricity sector
5
Newspapers
Informative online articles about the thermal solar
Yes
power station in Ashalim 6
Field visits
Visual impression concerning the operation of the
Partial
solar power station
Background
Motivation
Case study
Results
Conclusions
What’s next?
14
Avri Eitan
Results • The case study is divided into three sub-sections, each one describing an "exit-door" not taken, i.e., an opportunity to cancel or change the RE megaproject, which has been avoided due to various lock-ins. • These "exit doors" relate to different events that could have eased the change in the course of the RE megaproject.
Background
Motivation
Case study
Results
Conclusions
What’s next?
15
Part 1 Meeting RE targets through the Ashalim megaproject April 2007
August 2007
August 2007
Sep 2007
Sep 2007
March 2008
• “The State of Israel, with 300 days of sunshine a year, can lead the global effort to produce alternative energy such as solar energy” (Ehud Olmert(. • The government decided to establish large-scale solar power stations in Ahsalim (Decision 2178). • It appointed an interministerial committee comprising the Ministry of Finance (led by the accountant general), the Ministry of Energy, and the Electricity Authority. • The committee recommended promoting a public–private partnership tender (B.O.T) whose winner would be the bidder that agrees to accept the lowest payment. • The committee decided to recommend the use of thermal solar technology over PV solar technology – to be established in Ashalim.
• Another government decision (No. 3338) affirms the recommendation of the committee.
Background
Motivation
Case study
Results
Conclusions
What’s next?
16
Avri Eitan
Part 1 Meeting RE targets through the Ashalim megaproject Photovoltaic (PV)
Concentrated solar power (CSP)
VS Require low initial capital Allowed flexibility in the power station's installed capacity
Could be combined with gas power stations Enabling energy storage
Solar PV and thermal solar technologies were highly competitive at the time Background
Motivation
Case study
Results
Conclusions
What’s next?
17
Part 1 Meeting RE targets through the Ashalim megaproject
Background
Motivation
Case study
Results
Conclusions
What’s next?
18
Avri Eitan
Part 1 Meeting RE targets through the Ashalim megaproject April 2008
January 2009
March 2009
February 2011
• The tender's pre-qualification (PQ) documents were published - seven bidders passing the initial stage in September 2008. • The government announced a new target of 10% electricity production based on RE by 2020 (Decision 4450). • The official tender's documents were published. • The submission date for the bids was repeatedly delayed, and eventually was set to February 2011.
Only a single bid was submitted by Negev Energy, a company jointly owned by the Israeli Shikun VeBinui (50%) and the German Siemens AG (50%). Background
Motivation
Case study
Results
Conclusions
What’s next?
19
Avri Eitan
Part 1 Meeting RE targets through the Ashalim megaproject
Background Background
significant legal or financial obligations toward the single bidder.
* The committee could have addressed the reasons for the private sector’s lack of interest.
Motivation Motivation
Case study Case study
committee would fail to follow official government decisions concerning RE targets, backed by significant political support.
Results Results
Conclusions Conclusions
Organizational lock-in → Regret Costs
Regret Benefits
A decision to continue evaluate * At this with stage, the the project By and cancelling the the single State of Israel had no the bid. megaproject
What’s next? What next?
20
Part 1 Meeting RE targets through the Ashalim megaproject
Background
Motivation
Case study
Results
Conclusions
What’s next?
21
Part 2 Protecting the state’s reputation through the Ashalim megaproject The single bid reflected a price of 1.02 NIS (€0.26) to be paid by the state for every kWh – much higher than expectations of 0.8 NIS (€0.2).
Neglecting the megaproject at this stage might highlight the committee's failure to promote it (psychological lock-in).
A decision to conduct an independent cost analysis.
Background
Motivation
Case study
Results
Conclusions
What’s next?
22
Avri Eitan
Part 2 Protecting the state’s reputation through the Ashalim megaproject June
• The committee advised Negev Energy to resubmit its bid at a new price of 0.86 NIS (€0.215) per Kwh.
2012
Nov
• Siemens decides to disengage from thermal solar power stations due to their realization that solar PV was going to be the more dominant technology in the ensuing years.
2012
Negev Energy requested amendments to its ownership structure, enabling the Spanish company Abengoa to replace Siemens. Background
Motivation
Case study
Results
Conclusions
What’s next?
23
Avri Eitan
Part 2 Protecting the state’s reputation through the Ashalim megaproject
Regret Benefits Background Background
billion million.
NIS
(€525
both local and foreign players.
* The Siemens decision to stop its engagement with thermal solar technology was regarded as a strong indication that this technology should be abandoned.
Motivation Motivation
Case study Case study
Results Results
Conclusions Conclusions
Social lock-in → Regret Costs
PV power change allowed the project to continue: The approval *ofAlternative the ownership Harming the state’s station (at the same Negev Energy was announced the winner. reputation: as Influencing size) could save 2.1
What’s next? What next?
24
Part 2 Protecting the state’s reputation through the Ashalim megaproject
Background
Motivation
Case study
Results
Conclusions
What’s next?
25
Avri Eitan
Part 3 Legal obligations toward the Ashalim megaproject • The State of Israel signed a BOT agreement with Negev Energy. Sep 2013
• The interministerial committee approved the project's financial closure. July 2015
June 2016
• Abangua encountered financial distress and found itself on the verge of bankruptcy.
Negev Energy requested additional amendments enabling the Spanish company TSK Group (10%) and the Israeli Noy Fund (40%) to join Shikun VeBinui (50%) instead of Abangua. Background
Motivation
Case study
Results
Conclusions
What’s next?
26
Part 3 Legal obligations toward the Ashalim megaproject
Background
Electricity Authority's BOT begins agreement and2018. Full commercial operation in July estimations, the savings the financial closure could reach a total of with Negev Energy, the 4.25 billion NIS (€1.06 state had no legal way billion). of cancelling the megaproject. * Minimizing the concerns about the developer's capabilities.
Project lock-in → Regret Costs
Regret Benefits
A* decision continue with the megaproject: Accordingtoto the After the signing of the
Motivation
Case study
Results
Conclusions
What’s next?
27
Part 3 Legal obligations toward the Ashalim megaproject
Background
Motivation
Case study
Results
Conclusions
What’s next?
28
Avri Eitan
Conclusions: RE megaprojects Various lock-ins have influenced the Ashalim RE megaproject, preventing the adoption of the economically superior PV technology. These lock-ins have increased the regulators' regret cost, thus escalating their commitment to the RE megaprojects -resulting in its irreversibility. The discovered inflexibility of RE megaprojects contradicts the growing need of energy markets for new opportunities and degrees of freedom. However - megaprojects can also be evaluated using other aspects , which are often intangible and thus harder to quantify. Background
Motivation
Case study
Results
Conclusions
What’s next?
29
Avri Eitan
Conclusions: lock-ins in megaprojects The various lock-ins reinforced each other as the megaproject progressed, thus increasing regulators' regret cost over time. The power of the lock-in mechanism is emphasized in light of the events that could have reduce the cost of regret along the way – the three “exit doors”. The balance between lock-ins, which raise the cost of regret, and the ‘exit doors’, which may reduce the cost of regret, practically dictates the fate of megaprojects.
Background
Motivation
Case study
Results
Conclusions
What’s next?
30
Avri Eitan
Next: lock-ins in decentralized RE? Recent studies have also presented the increasing involvement of large private corporations in the field of RE.
According to some indications, these large corporations shape different lockins around RE, as they did with fossil fuel-based energy systems, in an attempt to regain power in the energy sector.
However, there remains much that we do not know about the nature of lockins in the context of RE and how such lock-ins are being tangibly shaped.
Background
Motivation
Case study
Results
Conclusions
What’s next?
32
Avri Eitan
Lock-ins in decentralized RE: My postdoc at Copernicus Institute of Sustainable Development
Background
Motivation
Case study
Results
Conclusions
What’s next?
33